Chilton Slips progressing well - OCC Update

Published on: 24/05/2016

Oxfordshire County Council have been carrying out works on the Chilton Slips to introduce north facing slip roads to both sides of the A34 at Chilton. Here is an update:

A great deal of work has now been done on building the new north facing slip roads at the Chilton Interchange. The northbound on slip earthworks are now around 75% complete and the southbound off slip road is 100% complete excluding the A34 “tie in” which is due to commence Easter time.

The culvert structure under the A34 is 30% complete the base slab has been poured with concrete and the wing walls are being prepared for concrete pouring. The east roundabout (Manor Court) is having kerbs laid, and is being prepared for surfacing.

The drainage works to the roundabout west of A34 on A4185 are nearly complete with sub base being placed prior to commencement installation  of kerbs and preparation for tarmac.

The work on the east roundabout is currently off the road (north of the A4185). Once we have the north side of the roundabout prepared, we will install traffic management to use the north side of the roundabout in the easterly direction and have one lane in operation to the south of the roundabout westbound.

Sign up for the Travel Choices bulletin by visiting: https://www.oxfordshire.gov.uk/cms/content/a34-chilton-interchange

You will receive regular news updates from the major project site teams to help you stay informed about each stage of the improvement works and travel choices to find active, environmentally friendly way of getting around Oxfordshire.

  All news stories

Got some news to share?

Tell us about your achievements and what you have been up to.
Submit a story

Submit News

Submission Terms and Conditions

Terms and conditions for submitting an event, news story or directory item onto Milton Park’s website: www.miltonpark.co.uk

  1. miltonpark.co.uk is owned and run by MEPC Ltd, owners and managers of Milton Park, Oxfordshire
  2. All submissions are forwarded to the Marketing Executive for approval before upload
  3. Content submitted may be subject to change
  4. Content must be written in good English and grammatically correct
  5. If the submission is not deemed suitable or relevant it will not be uploaded
  6. Content must be clear, easy to read, understandable and relevant to the occupiers of Milton Park
  7. Once uploaded, items are subject to deletion at any time
  8. Upon submission, you will receive a confirmation email with a copy of these terms and conditions for reference
  9. Upon submission, items will be uploaded within 3 working days if suitable
  10. Classifieds are deleted after six months of upload
  11. News stories are archived monthly and remain on the Website for one year
  12. Events are archived monthly and remain on the Website for one year
  13. Companies listed on the website will be removed when leaving Milton Park